Project Start | Summer 2011 |
Project Completion | Summer 2014 |
Contractor | Sema Construction, Inc. |
Bid Amount | $14.8 million |
Funding | Transportation Uniform Mitigation Fund Measure A Palm Springs Cathedral City Rancho Mirage |
Project Overview
- Widen existing overcrossing on each side to accommodate a total of six lanes of traffic, including bike lanes on each side
- Modify on and off-ramps: – (Note: All on-ramps will be setup for future metering)
- Westbound I-10
- New, one-lane metered loop on-ramp from northbound Date Palm Drive
- Realigned, two-lane metered on-ramp from southbound Date Palm Drive
- Realigned, two-lane off-ramp
- Eastbound I-10
- New, one-lane metered loop on-ramp from southbound Date Palm Drive
- Realigned, two-lane metered on-ramp from northbound Date Palm Drive
- Realigned, two-lane off-ramp
- Westbound I-10