Project Start | February 2010 |
Project Completion | Early 2012 |
Contractor | SEMA Construction |
Bid Amount | $25.5 million |
Funding | American Recovery and Reinvestment Act of 2009 Interstate Maintenance Discretionary Transportation Uniform Mitigation Fund County of Riverside Palm Springs Cathedral City Rancho Mirage |
Project Overview
- Add new eight-lane overcrossing and extend Bob Hope Drive to Varner Road
- Add new interchange just west of the existing Ramon Road Interchange
- Add new six-lane bridge over Union Pacific Railroad
- Modify on and off-ramps – (Note: All on-ramps will be setup for future metering)
- Westbound I-10
- New, two-lane on-ramp from Bob Hope Drive
- New, three-lane off-ramp at Bob Hope Drive
- Eastbound I-10
- New, two-lane on-ramp from Bob Hope Drive
- New, two-lane off-ramp at Bob Hope Drive
- Westbound I-10
- Realign Rio Del Sol
- Widen portions of Varner Road
- Remove all Ramon Road ramps, except for eastbound on-ramp