Ramp closures will take place on I-10 at Jefferson Street October 2 – 6. The purpose of these closures is to continue bridge and roadway construction activities.
Closure Schedule
EB on-ramp day:
Monday through Friday, October 2 – 6, 2017. 5:00 AM – 5:00 PM
EB on-ramp night:
Monday through Friday, October 2 – 6, 2017. 7:00 PM – 5:00 AM
EB off-ramp day:
Monday through Friday, October 2 – 6, 2017. 5:00 AM – 5:00 PM
EB off-ramp night:
Monday through Friday, October 2 – 6, 2017. 7:00 PM – 5:00 AM
Detour for closure of EB I-10 On-ramp at Jefferson St.
- Go east on Varner Rd. to Monroe St.
- Turn right at Monroe St.
- Turn left at the EB I-10 on-ramp.
Detour for closure of EB I-10 Off-ramp at Jefferson St.
- Go east on I-10 exit at Monroe St.
- Turn left at Monroe St.
- Turn left at Ave. 42/Varner Rd. back to Jefferson St.